Example Base Year Implementation Timeline
Planning
Project kickoff
Apr 1
May
Jun
Jul
Aug
Define project scope
10d
Identify stakeholders
7d
Confirm reporting frameworks
7d
Select base year
Apr 24
Data Collection
Inventory existing data
14d
Identify data gaps
5d
Develop collection plan
7d
Collect historical data
21d
Validate data quality
10d
Policy Development
Draft base year policy
10d
Define recalculation thresholds
5d
Establish documentation
5d
Get management approval
7d
Policy finalization
May 25
Implementation
Configure data systems
14d
Train relevant teams
7d
Complete base year calculations
14d
Jul 25
External verification
21d